CloudEngine 16800 Series Switches Hardware Installation and Maintenance Guide (V200)
Installing the CloudEngine 16804
Context
- Move the device near the cabinet or rack before the installation.
- For convenient maintenance, leave at least 1000 mm of clearance at the front and rear of the device. Do not install the device against a wall.
- Keep the tweezers and wrenches delivered with the device for future use.
- If the device is delivered with main control boards, interface boards, SFUs, and power modules installed, you are advised to remove them before installing the device into a cabinet or rack.
- For the CloudEngine 16804, reserve sufficient space on the top of the CloudEngine 16804 for power cable routing.
- CloudEngine 16804 DC chassis: reserved space ≥ 2U
- CloudEngine 16804 AC & high-voltage DC chassis: reserved space ≥ 1U
- A maximum of three CloudEngine 16804 devices can be installed in each cabinet.
- You can use Huawei expandable guide rails (expandable between 500 mm and 850 mm) or separately purchased guide rails or tray with sufficient load bearing capacity.
Tools and Accessories
- Scissors
- Flat-head screwdriver
- Phillips screwdriver
- Marker
- CloudEngine 16804 installation template (CloudEngine 16804 and 16808 Quick Installation Guide)
- Floating nuts and matching screws
- Floating nut mounting bar
- Expandable guide rails and matching screws
Procedure
- Mark the mounting holes for the expandable guide rails and mounting brackets on the guide rails.
Positions of mounting brackets only need to be marked on the front mounting rails, whereas positions of expandable guide rails must be marked on both the front and rear mounting rails. Keep the mounting holes on the front and rear mounting rails on the same horizontal plane.
- Install floating nuts in the marked mounting holes.
- You can use a floating nut mounting bar to facilitate installation of floating nuts.
- When installing the CloudEngine 16804, eight floating nuts are used to secure the mounting brackets, and 10 floating nuts are used to secure the guide rails (two for the front end and three for the rear end of each guide rail).
Figure 5-4 Installing floating nuts - Install expandable guide rails.
- When installing expandable guide rails, ensure that the front and rear ends of each guide rail are on the same horizontal plane.
- For a third-party cabinet or rack, if you do not use the expandable guide rails delivered with the device, use a tray (with a minimum load bearing capacity of 324 kg) instead.
- Install the device in the cabinet or rack.