SUN2000-(3KTL-10KTL)-M1 User Manual
M:SUN2000-3KTL-M1,SUN2000-4KTL-M1,SUN2000-5KTL-M1,SUN2000-6KTL-M1,SUN2000-8KTL-M1,SUN2000-10KTL-BEM1,SUN2000-10KTL-M1;Smart PV inverter, Smart PV Controller, Cascading, AFCI, dry contact scheduling, dry contact function, rapid shutdown
M:SUN2000-3KTL-M1,SUN2000-4KTL-M1,SUN2000-5KTL-M1,SUN2000-6KTL-M1,SUN2000-8KTL-M1,SUN2000-10KTL-BEM1,SUN2000-10KTL-M1;Smart PV inverter, Smart PV Controller, Cascading, AFCI, dry contact scheduling, dry contact function, rapid shutdown
About This Document
Overview
This document describes the SUN2000-3KTL-M1, SUN2000-4KTL-M1, SUN2000-5KTL-M1, SUN2000-6KTL-M1, SUN2000-8KTL-M1, SUN2000-10KTL-BEM1 and SUN2000-10KTL-M1 (SUN2000 for short) in terms of their installation, electrical connections, commissioning, maintenance, and troubleshooting. Before installing and operating the SUN2000, ensure that you are familiar with the features, functions, and safety precautions provided in this document.
The SUN2000-8KTL-M1, SUN2000-10KTL-BEM1 and SUN2000-10KTL-M1 are not applicable to Australia.
Intended Audience
This document is applicable to:
- Installers
- Users
Symbol Conventions
Symbol |
Description |
---|---|
Indicates a hazard with a high level of risk which, if not avoided, will result in death or serious injury. |
|
Indicates a hazard with a medium level of risk which, if not avoided, could result in death or serious injury. |
|
Indicates a hazard with a low level of risk which, if not avoided, could result in minor or moderate injury. |
|
Indicates a potentially hazardous situation which, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. Notice is used to Addedress practices not related to personal injury. |
|
Supplements the important information in the main text. NOTE is used to Addedress information not related to personal injury, equipment damage, and environment deterioration. |
Change History
Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues.
Issue 26 (2025-07-25)
- Updated 2.3.2 Product Nameplate.
- Updated 5.2 Installation Preparation.
- Updated 5.8.2 Connecting the RS485 Communications Cable (Smart Power Sensor).
- Updated 5.7 (Optional) Installing the Smart Dongle and Anti-theft Components.
- Updated 5.8.7 Connecting the Grid Scheduling Signal Cable.
- Updated 10.1 SUN2000 Technical Specifications.
Issue 25 (2025-07-01)
- Updated 2.1 Product Introduction.
- Updated 2.3.2 Product Nameplate.
- Updated 7.1.6 Limit on Power Purchased from Grid.
- Updated 7.2.6 Limit on Power Purchased from Grid.
- Added 7.1.5 Setting the Energy Measurement Mode.
- Added 7.2.5 Setting the Energy Measurement Mode.
Issue 24 (2025-05-08)
- Updated 2.1 Product Introduction.
Issue 23 (2025-04-22)
- Updated 5.2 Installation Preparation.
- Added 7.1.6 Limit on Power Purchased from Grid.
- Added 7.2.6 Limit on Power Purchased from Grid.
Issue 22 (2025-01-10)
- Updated 2.1 Product Introduction.
- Updated 5.2 Installation Preparation.
- Updated 5.8 (Optional) Connecting the Signal Cable.
- Added 5.8.4 Connecting RS485 Communications Cables (EMMA).
- Added 5.8.5 Connecting RS485 Communications Cables (EMMA and Battery).
- Added 5.8.6 Connecting RS485 Communications Cables (SmartGuard).
- Updated 7 Power-On and Commissioning.
- Updated 10.1 SUN2000 Technical Specifications.
- Updated A Grid Code.
- Added B Connecting to the Inverter on the App.
- Added C Connecting to the EMMA on the App.
Issue 21 (2024-11-01)
Updated 5.8.3 Connecting an RS485 Communications Cable (Between a Power Meter and a Battery).
Issue 20 (2024-10-23)
Updated 5.8.7 Connecting the Grid Scheduling Signal Cable.
Issue 19 (2024-09-06)
Added 7.3.1 DRM (Australia AS4777).
Issue 18 (2024-06-24)
Delete Locating Insulation Resistance Faults.
Issue 17 (2024-01-12)
- Updated 5.2 Installation Preparation.
- Updated 5.8.2 Connecting the RS485 Communications Cable (Smart Power Sensor).
- Updated 8.3 Troubleshooting.
- Updated 10.1 SUN2000 Technical Specifications.
- Updated A Grid Code.
Issue 16 (2023-11-02)
Updated 5.4 Connecting the AC Output Power Cable.
Issue 15 (2023-09-30)
Updated 7 Power-On and Commissioning.
Issue 14 (2023-09-06)
Updated A Grid Code.
Issue 13 (2023-08-23)
Updated E Rapid Shutdown.
Issue 12 (2023-07-30)
- Updated About This Document.
- Updated 2.1 Product Introduction.
- Updated 5.2 Installation Preparation.
- Updated 10.1 SUN2000 Technical Specifications.
Issue 11 (2023-04-07)
- Updated 5.8.9 Connecting the NS Protection Signal Cable.
- Updated A Grid Code.
Issue 10 (2023-02-07)
- Updated 2.1 Product Introduction.
- Updated 5.2 Installation Preparation.
- Updated 5.8.2 Connecting the RS485 Communications Cable (Smart Power Sensor).
- Updated 5.8.9 Connecting the NS Protection Signal Cable.
- Updated 7 Power-On and Commissioning.
Issue 09 (2022-10-10)
- Updated 5.2 Installation Preparation.
- Updated 5.4 Connecting the AC Output Power Cable.
Issue 08 (2022-06-30)
- Updated 5.2 Installation Preparation.
- Updated 7 Power-On and Commissioning.
- Updated 10.1 SUN2000 Technical Specifications.
- Updated A Grid Code.
- Added F AI Energy Management Assistant (EMMA).
Issue 07 (2022-03-04)
- Updated 5.8.2 Connecting the RS485 Communications Cable (Smart Power Sensor).
- Updated D Resetting Password.
- Updated E Rapid Shutdown.
Issue 06 (2021-12-20)
- Updated 7 Power-On and Commissioning.
Issue 05 (2021-11-24)
Updated 10.1 SUN2000 Technical Specifications.
Issue 04 (2021-08-10)
- Updated 2.1 Product Introduction.
- Updated 5.5 Installing DC Input Power Cables.
- Updated 5.6 (Optional) Connecting Battery Cables.
- Updated 5.8 (Optional) Connecting the Signal Cable.
- Updated 7 Power-On and Commissioning.
Issue 03 (2021-02-01)
- Updated 4.3.2 Space Requirements.
- Updated 5.8.2 Connecting the RS485 Communications Cable (Smart Power Sensor).
- Updated 6.2 SUN2000 power-on.
- Updated 8.3 Troubleshooting.
Issue 02 (2020-11-20)
- Updated 7 Power-On and Commissioning.
Issue 01 (2020-09-30)
This issue is used for first office application (FOA).