5.2 Installation Preparation
If a Smart Dongle is configured, it is recommended that you install it before connecting the signal cable.
No. |
Component |
Description |
Source |
---|---|---|---|
A |
PV module |
|
Prepared by users |
B |
(Optional) Smart PV optimizer |
Supported models: SUN2000-(450W-P, 600W-P, 450W-P2) and MERC-600W-PA04. |
Purchased from Huawei |
C |
(Optional) Battery |
The LUNA2000 batteries can be connected to the SUN2000. |
Purchased from Huawei |
D |
(Optional) Smart Dongle |
Supported models:
|
Purchased from Huawei |
E |
(Optional) SUN2000 |
Select a proper model as required. |
Purchased from Huawei |
F |
(Optional) SmartLogger |
Select a proper model as required. |
Purchased from Huawei |
G |
(Optional) Power meter1 |
Recommended meter models: DTSU666-H, YDS60-C242, DTSU71 and DHSU1079-CT3 |
Purchased from Huawei |
H |
(Optional) Power grid scheduling device |
Select the devices that meet the power grid scheduling requirements. |
Provided by the local power grid company |
I |
(Optional) Rapid shutdown switch |
Select a proper model as required. |
Prepared by users |
J |
AC switch |
To ensure that the inverter can be safely disconnected from the power grid when an exception occurs, connect an AC switch to the AC side of the inverter. Select an appropriate AC switch in accordance with local industry standards and regulations. Huawei recommends the following switch specifications: Recommended: a three-phase AC circuit breaker with a rated voltage greater than or equal to 380 V AC and a rated current of:
|
Prepared by users |
K |
(Optional) Smart Backup Box |
Select a proper model as required. |
Purchased from Huawei |
L |
EMMA |
Supported models: EMMA-A01 and EMMA-A02 |
Purchased from Huawei |
M |
SmartGuard |
The three-phase SmartGuard can be used to switch the inverter between on-grid and off-grid states. Supported models: SmartGuard-63A-T0 and SmartGuard-63A-AUT0 |
Purchased from Huawei |
Note 1: For details about meter operations, DTSU666-H 100 A and 250 A Smart Power Sensor User Manual, DTSU71 Smart Power Sensor Quick Guide, DHSU1079-CT Smart Power Sensor Quick Guide, or YDS60-C24 Smart Power Sensor Quick Guide. Note 2: SUN2000MA V100R001C00SPC150 and later versions can connect to YDS60-C24 power meters. Note 3: SUN2000MA V100R001C00SPC160 and later versions can connect to DTSU71 and DHSU1079-CT power meters. Note 4:
|
No. |
Name |
Type |
Recommended Specifications |
---|---|---|---|
1 |
DC input power cable |
Common outdoor PV cable in the industry (Recommended model: PV1-F) |
|
2 |
(Optional) Battery cable |
||
3 |
(Optional) Signal cablea |
Outdoor shielded twisted pair |
|
4 |
AC output power cableb |
Outdoor copper cable |
|
5 |
PE cable |
Single-core outdoor copper-core cable |
Conductor cross-sectional area: ≥ 4 mm2 |
Note a: When the smart power sensor and battery are connected to the SUN2000 at the same time, use a cable core with a cross-sectional area of 0.2 mm2 to 0.5 mm2. Note b: The minimum cable diameter depends on the fuse rating on the AC side. |
- The minimum cable diameter should comply with the local cable standard.
- Factors influencing cable selection are as follows: rated current, type of cable, routing method, ambient temperature, and maximum desired line losses.